Haul route in WA wheatbelt region gets PolyCom upgrade
West Australian PolyCom distributor Betta Roads recently worked with a Shire to upgrade a grain haul route with PolyCom in the wheatbelt region.
The area is the source of nearly two thirds of the state's wheat production, half of its wool production, and a range of other agricultural and pastoral products.With considerable effort made to support the efficient transport of goods out of the region, the existing road maintenance regime for one local shire was becoming unrealistic in both cost and resource management.
In a road widening and reconstruction project, the Shire decided to use PolyCom Stabilising Aid to strengthen the base course.
Three years on, the Shire has used PolyCom on approximately 15 kilometres of road per year to reduce degradation and road failure, and overall wear on the sealed surface.
The PolyCom stabilisation has created a far better outcome for this problem area, resulting in:
Reduced deformation in the outer wheel path of the treated roads
Reduced punching of the aggregate into the road surface
Reduced flushing of bitumen at the surface.
Maintenance on the PolyCom treated sections of road have been reduced, making for a sustainable solution where resources can be utilised to do other works required.
Traditional road construction methods suggest there is an upper limit to CBR readings that will result in cracking. However, by maintaining flexibility of the treated pavement and raising overall pavement strength, PolyCom has allowed maintenance crews to achieve much higher CBR values using the material already present in these roads without failure. This factor allows use of lower grade materials that will generate a superior outcome.
The use of PolyCom has saved considerable resources for the Shire, and lead to fewer complaints from the public.
23 Dec 2016